Project Description

MV Dole America

Repair project: Cargo hold damage

Dole America cargo hold insulation

Seawater damage in two complete cargo holds

Total re-insulation was done in 28 days from start of work until loading of cargo.
Work was done on 24 h shift with 130 persons.

  • Total stripping all insulation in two cargo holds (0n 8 decks).
  • Insulation and lining of tanktop.
  • Insulation and lining of shipssides and bulkheads.
  • Insulation and lining under deck.
  • Installation of air cooler units.
  • Installation of aluminum gratings.